Outflow Project Update

Posted by Crystal Lake Improvement Association
2 years ago | November 6, 2021


The City of Burnsville provided an update to CLIA from the Engineering Department.  The outlet project has been going well.  They are pouring the foundation this week and will be forming the walls later this week or early next.  The latest update was that they’d be working on site restoration (disturbed area seeding and other miscellaneous wrap up) during the week of Nov 22 so they are projecting the project will be done before thanksgiving.  That could change but that’s what it’s looking like right now.